New Project - West Quay Marina
21st March 2023
Woodmace are currently on site in Poole for the West Quay Marina project for our client London Land Construction Ltd, undertaking groundworks, substructure and drainage.
The works duration is 39 weeks, starting from February 2023 and includes:
• RC transfer deck works also circa 8000m2
• 1500T of rebar in the foundations and transfer structure
• Dewatering and working in tidal environment
• Precast superstructure to be carried out by others
• All 278 and drainage works